Notice of Exemption for Mark Cairns Under Section 90(1)(b) of the Electricity Industry Act 2010
In accordance with section 90(1)(b) of the Electricity Industry Act 2010 (“Act”), the Electricity Authority (“Authority”) gives the following notice.
Mark Cairns (“Mr Cairns”) is exempted from compliance with sections 75, 77–79 and 88 of the Act, in relation to his appointment as a director of the Auckland International Airport Limited (AIAL) board while he is also a director of the Meridian Energy Limited (“Meridian”) board.
This exemption will expire on 31 October 2023.
This exemption is subject to the following conditions:
(1) While Mr Cairns is a director of both AIAL and Meridian:
(2) On or before 31 October 2023, Mr Cairns will confirm to the Authority, in writing, that the cross-directorship to which this exemption applies has ceased.
(3) This exemption is specific to the cross-involvements created through Mr Cairns’ directorships in both the AIAL board and the Meridian board. It does not extend to any other directorships, interest or future cross-involvement of Mr Cairns.
This exemption comes into force on the date it is notified in the New Zealand Gazette.
Dated at Wellington this 13th day of June 2022.
For and on behalf of the Electricity Authority:
Dr NICOLA CRAUFORD, Chair, Electricity Authority.