Notice Type
Authorities/Other Agencies of State
Notice Title

Electricity Industry (Exemption No. 262 (Nova Energy Limited)) Exemption Notice 2017

Under section 11 of the Electricity Industry Act 2010 (“Act”), the Electricity Authority gives the following notice.

Notice

1. Title and commencement—(1) This notice is the Electricity Industry (Exemption No. 262 (Nova Energy Limited)) Exemption Notice 2017.

(2) This notice comes into force on the day after the date it is notified in the New Zealand Gazette.

2. Exemption—(1) Nova Energy Limited (“Nova”) is exempted from complying with the obligation in clause 10.24(c) of the Electricity Industry Participation Code 2010 (“Code”) not to use subtraction to determine submission information.

(2) This exemption applies only to ICP 0008201110WM5F5.

3. Term—This exemption expires on the earlier of:

  1. the close of 28 February 2018; and
  2. the completion date of a new supply point to Taharoa Village upstream of New Zealand Steel Limited’s Taharoa ironsands mine.

4. Reasons for granting the exemption—The reasons for granting this exemption are:

  1. the exemption from clause 10.24(c) of the Code will allow Nova to use subtraction to determine submission information, even though ICP 0008201110WM5F5 is not also a network supply point (NSP);
  2. deriving the submission information from the metering installations by subtraction is as accurate as it would be if it was derived using directly metered data;
  3. the exemption will have no impact on any other participant or service provider, and will not affect any other Code provision; and
  4. the exemption meets the requirements in section 11(2) of the Act.

Dated at Wellington this 30th day of August 2017.

For and on behalf of the Electricity Authority:
SUSAN PATERSON, onzm, Member, Electricity Authority.