1. Pursuant to section 38(3)(b) of the Electricity Industry Act 2010 ("Act"), the Electricity Authority ("Authority") gives notice of the making of the Electricity Industry Participation (HVDC Link Bipole Control System Testing) Code Amendment 2013.
2. The amendment comes into force on 26 September 2013.
3. The amendment adds a new exception to the requirement that Transpower must comply with the interconnection asset capacity and grid configuration requirements in clause 12.111 of the Code. The exception will apply if the HVDC link is configured in bipole in accordance with a commissioning plan or test plan.
4. The amendment also introduces data requirements to support the modelling of bipole configurations in the market systems.
5. The amendment will support the commissioning of the new HVDC link bipole control system.
6. In accordance with section 39(3)(a) of the Act,
the Authority is satisfied on reasonable grounds
that the nature of the amendment is technical and
non-controversial. Therefore the Authority has neither prepared and publicised a regulatory statement, nor consulted on the amendment and a regulatory statement.
7. Copies of the amendment and the Code are available on the Authority's website at
www.ea.govt.nz/act-code-regs/code-regs/
8. Copies of the amendment and the Code may also be inspected free of charge or purchased from the Electricity Authority, Level 7, ASB Bank Tower, 2 Hunter Street, Wellington.
Dated at Wellington this 26th day of August 2013.
DR THOMAS BRENT LAYTON, Chairperson, Electricity Authority.